- 05/06/14 Construction List
- 16/06/14 Site scrape
- 19/06/14 Site cut, piering
- 26/06/14 Slab poured
- 30/06/14 Stormwater pipes, taps
- 01/07/14 Electricity trenched, private pole erected
- 04/07/14 Termite barrier, 5T machine over slab
- 07/07/14 Frames delivered
- 08/07/14 Frame erected
- 09/07/14 Roof trusses delivered, windows delivered. Stacker door fell off truck.
- 10/07/14 Crane, roof trusses
- 12/07/14 Windows put in
- 14/07/14 Internal plumbing rough in
- 15/07/14 Soft waste bin, meter box, bricks delivered
- 16/07/14 Sand delivery, skip bin
- 28/07/14 Bricklayer commences
- 22/08/14 Guttering and fascia
- 25/08/14 Bricklaying complete
- 29/08/14 Safety rails for roof erected
- 30/08/14 Roof battens
- 01/09/14 Roof completed
- 03/09/14 SMS for roof completion, yard clean up
- 05/09/14 Eaves
- 08/09/14 New SS
- 09/09/14 Bricks cleaned
- 10/09/14 Front porch "ceiling" and eaves, alfresco eaves
- 11/09/14 Water tank delivered
- 12/09/14 Electrical rough-in
- 16/09/14 Electrical Walk Through with SS
- 17/09/14 Insulation
- 18/09/14 Gyprock start
- 19/09/14 Gyprock finish
- 23/09/14 Cornices start and finish
- 29/09/14 Down pipes
- 30/10/14 Garage door, waterproofing
- 01/10/14 Front door, laundry door, internal doors, lock up.
- 03/10/14 Water tank connected/plumbing
- 04/10/14 Painting, 1st coat
- 07/10/14 Fibreflash waterproofing 2nd stage
- 08/10/14 Kitchen, bathroom, laundry cabinets delivered
- 09/10/14 Kitchen and laundry cabinets installed
- 10/10/14 Tile delivery, electrical points cut out, sanding
- 11/10/14 Painting, front door painted, sand delivery
- 12/10/14 Painting
- 13/10/14 Tiling start
- 15/10/14 Progress claim
- 17/10/14 SMS Tiling complete
- 18/10/14 Painting
- 21/10/14 Painting exterior, smart wiring (data points),TV bracket, aerial
- 23/10/14 Electrical
- 24/10/14 Tiler finishing off alfresco tiling
- 25/10/14 Carpentry for wardrobes, pantry, linen cupboard
- 28/10/14 Air conditioning installed
- 29/10/14 Taps, toilets, shower heads, bathtub
- 01/11/14 House cleaned inside
- 03/11/14 Front yard dug up looking for sewer waste pipe
- 04/11/14 Mirrors, shower screens, SMS, blue tape
- 05/11/14 Floor
- 06/11/14 Floor, flyscreens, portaloo removed
- 10/11/14 Splashback installed
- 11/11/14 Air con control panel and thermostat installed
- 12/11/14 Skirting boards, towel rails, toilet paper holders
- 14/11/14 Builder's fence removed
- 15/11/14 Yard cleanup, plantation shutters
- 17/11/14 Area Manager inspection
- 18/11/14 Roller blinds