Pages

Timeline


    • 05/06/14 Construction List
    • 16/06/14 Site scrape
    • 19/06/14 Site cut, piering
    • 26/06/14 Slab poured
    • 30/06/14 Stormwater pipes, taps
    • 01/07/14 Electricity trenched, private pole erected
    • 04/07/14 Termite barrier, 5T machine over slab
    • 07/07/14 Frames delivered
    • 08/07/14 Frame erected
    • 09/07/14 Roof trusses delivered, windows delivered. Stacker door fell off truck.
    • 10/07/14 Crane, roof trusses 
    • 12/07/14 Windows put in
    • 14/07/14 Internal plumbing rough in
    • 15/07/14 Soft waste bin, meter box, bricks delivered
    • 16/07/14 Sand delivery, skip bin
    • 28/07/14 Bricklayer commences
    • 22/08/14 Guttering and fascia
    • 25/08/14 Bricklaying complete
    • 29/08/14 Safety rails for roof erected
    • 30/08/14 Roof battens
    • 01/09/14 Roof completed
    • 03/09/14 SMS for roof completion, yard clean up
    • 05/09/14 Eaves
    • 08/09/14 New SS
    • 09/09/14 Bricks cleaned
    • 10/09/14 Front porch "ceiling" and eaves, alfresco eaves
    • 11/09/14 Water tank delivered
    • 12/09/14 Electrical rough-in
    • 16/09/14 Electrical Walk Through with SS
    • 17/09/14 Insulation
    • 18/09/14 Gyprock start
    • 19/09/14 Gyprock finish
    • 23/09/14 Cornices start and finish
    • 29/09/14 Down pipes
    • 30/10/14 Garage door, waterproofing
    • 01/10/14 Front door, laundry door, internal doors, lock up.
    • 03/10/14 Water tank connected/plumbing
    • 04/10/14 Painting, 1st coat
    • 07/10/14 Fibreflash waterproofing 2nd stage
    • 08/10/14 Kitchen, bathroom, laundry cabinets delivered
    • 09/10/14 Kitchen and laundry cabinets installed
    • 10/10/14 Tile delivery, electrical points cut out, sanding
    • 11/10/14 Painting, front door painted, sand delivery
    • 12/10/14 Painting
    • 13/10/14 Tiling start
    • 15/10/14 Progress claim
    • 17/10/14 SMS Tiling complete
    • 18/10/14 Painting
    • 21/10/14 Painting exterior, smart wiring (data points),TV bracket, aerial
    • 23/10/14 Electrical
    • 24/10/14 Tiler finishing off alfresco tiling
    • 25/10/14 Carpentry for wardrobes, pantry, linen cupboard
    • 28/10/14 Air conditioning installed
    • 29/10/14 Taps, toilets, shower heads, bathtub
    • 01/11/14 House cleaned inside
    • 03/11/14 Front yard dug up looking for sewer waste pipe
    • 04/11/14 Mirrors, shower screens, SMS, blue tape
    • 05/11/14 Floor
    • 06/11/14 Floor, flyscreens, portaloo removed
    • 10/11/14 Splashback installed
    • 11/11/14 Air con control panel and thermostat installed
    • 12/11/14 Skirting boards, towel rails, toilet paper holders
    • 14/11/14 Builder's fence removed
    • 15/11/14 Yard cleanup, plantation shutters
    • 17/11/14 Area Manager inspection
    • 18/11/14 Roller blinds